Aero Solutions enables our clients to expedite their deployments of macrocell and small cell wireless networks. With over 15 years of continual innovation, performing over 4,000 design/build tower collocations, and extensive small cell engineering and project management experience, we have established ourselves as a national leader in the wireless infrastructure market.At the heart of our company, we are innovators, led by technical excellence and a clear understanding of what happens in the field. Our delivery team works tirelessly, year after year, to keep us ahead of the curve by providing forward thinking solutions and outstanding customer service.
telecomm, telecommunications engineering, tower reinforcement, macro cell, small cell, wireless, wireless infrastructure market, wireless optimization, tower collocations, telecomm innovation, wireless networks, small cell engineering, macro cell engineering, expedite deployments, municipal consulting, telecomm consulting, telecomm experts, telecomm project management, wireless industry leader, wireless industry experts, turnkey collocations, technical field service, telecomm field service, smart poles, rooftop deployment, telecomm innovators,
690
post-template-default,single,single-post,postid-690,single-format-standard,ajax_fade,page_not_loaded,,select-child-theme-ver-1.0.0,select-theme-ver-3.7,side_area_uncovered,wpb-js-composer js-comp-ver-5.0.1,vc_responsive
 

Lattice Tower Upgrades at Hoover Dam

Lattice Tower Upgrades at Hoover Dam

portfolio HooverLattice Tower Upgrades at Hoover Dam  |  Nevada-Arizona Border

Project Description:

This tower is located adjacent to Hoover Dam and provides cell coverage for this area. To improve cell coverage at this location, a cell carrier contacted SBA Communications with a request to collocate an additional 18 panel antennas on the structure at 212 feet and an additional 12 antennas at 245 feet. SBA Communications evaluated the structure with proposed loading and determined the tower was structurally insufficient for the new antennas. Given Hoover Dam’s status as National Critical Infrastructure and increased security measures, a limited construction window was granted that required a solution providing expedient installation with minimal carrier disruption. This project focused on providing a turn-key solution for the modification and placement of new antennas and equipment to support the cell carrier’s effort to provide improved cell coverage in the area.

Aero Solutions Role:

Aero Solutions provided a turn-key solution using non-welded reinforcing elements to bring the tower into compliance with the new antenna loading. An engineered bolt-on solution was developed to reinforce the tower at elevations of 0-50 feet, 143 feet, 183 feet, 199 feet and 213 feet. Aero’s modification was completely non-welded, eliminating any risk of fire and increasing the safety at this sensitive site. Upon completion of the modification, the tower overstress ratios were lowered to below 100 percent.

Technical Description:

Tower Type: Four-sided self support
Height: 265 feet
Modification Date: 2006
Client: AAT Communications  [ Tower now owned by SBA Communications ]

Self Support Hoover Dam